The house-building system “Ecocube"

The house-building system “Ecocube"

ECOCUBE is a system which allows for building energy-efficient, environmentally friendly, economical houses from natural renewable materials.

Industry:

Smart building

Smart building

TRL:

2 → 5

Project duration:

6 months

Challenge

Initially, the customer approached us with the challenge of developing a new version of the fundamental construction component – ecocube – through the advancement of the existing technology of the 4th generation. The inability of the building blocks to adapt to contemporary automated production was the main flaw of the old ecocube generation. Because of this EnCata’s primary objective was the improvement of the fourth-generation ecocube for fully automated mass production.

An ecocube is a basic building element made up of a membrane and a frame. Natural filler is used to fill the inside space, making the module both environmentally friendly and affordable to produce. A low-rise private house can be assembled entirely using a set of these components.

The filling of the final product is made from natural fibers, including rye, wheat, oat, and other grasses and cereals, as well as flax and campfire waste, cane and sunflower husks. 

At the beginning of the project, EnCata’s engineers faced 3 major challenges:

  • modifying the fundamental building block to allow for automated mass production while keeping the cost of the currently available technology at a minimum and preserving the structure's stability and strength in accordance with international building codes;
  • developing technologies that enable high productivity (1180 blocks per 1 working shift) without complicating the construction of houses;
  • implementing automatic control of the filler density, while minding that the density of the various natural fiber components varies.

Our Role

  • Concept Development
  • Industrial Design
  • Mechanical Engineering
  • FEA
  • CFD
  • 3D modeling
  • Design for Manufacturing
  • Prototyping
  • Manufacturing Consultancy

Technologies Used

3D modeling
Industrial Design
FEA
CAD development
CFD
Engineering R&D
Design for Manufacturing
Laser cutting
Milling

For Enterprises

R&D + design + manufacturing under ONE roof
Scale up and down your team
Intergrated hardware + software development
New technologies and research 

For Startups

MVP and POC prototypes
Affordable consultancy rates
All IP is yours
In-house batch production

Approach & Solution

The customer's idea to modify the basic technology for mass manufacturing was completely carried out by our engineers.

The preparation for automated production was done in 2 directions:

  1. Optimizing the block design components by reducing the thickness of the plywood grid’s ribs of the inter storey slab. Strength calculations and tests on a physical prototype made it possible to find the optimal thickness of the ribs. The decreased thickness resulted in faster technological advancement and a shorter processing time for the ribs. The inter storey slab’s plywood grid was also optimized in this way.
    The materials used for the blocks' edges were also changed for thinner ones, which helped save the time it took to prepare the blocks for assembly thanks to faster technological processes.
  2. Optimization of the block design involved moving away from the 'puzzle concept.' The original 'puzzle concept' included three types of blocks:
    1. blocks with fasteners only;
    2. blocks with fasteners and openings for fasteners;
    3. blocks with openings for fasteners only. Instead, the engineers proposed designing units with only openings, connected by independent fasteners.

This modification made it possible to replace a longer and more expensive milling procedure with a standard furniture machine, which saved 45% of the time to produce a single block.

The original block’s fastener system significantly constrained the team’s ability to develop the technology for mass manufacturing. However, EnCata’s engineers employed a distinct approach to the fastening mechanism and created “standard locks” (see pic.3) linking the blocks as independent pieces as opposed to being a component of each block. This made it feasible not only to accelerate the production, but also to simplify the installation of the house box on the construction site.

The developed fastener system made it possible to produce 1180 blocks in an 8-hour work shift in just one production line. Two issues were resolved at once by minimizing milling and substituting it with machinery for furniture production:

  • it was possible to produce 83 blocks every hour, which was the required amount;
  • the procedure became less expensive as a result of using less complex and costly machinery, and there were less operations required to prepare the fundamental block for combining with other blocks.

The automatic weighing of natural components supplied into the Ecocub was used to implement automatic density control. The density of the natural components has an impact on the thermal insulation. Our engineers approached this issue from a distinct perspective and asked a different question: “What amount of straw inside the block will offer the necessary thermal insulation?”

Computer simulations revealed a weight fluctuation of the fiber components of 60(-/+ 10kg). The range of allowable variances in 10kg made it possible to balance out different densities of the components while also offering the right amount of thermal insulation. In practice, loading of blocks with biomass was carried out in the following method: biomass fed into the intermediate block (which served as the weight batcher) from the storage block, after reaching the desired volume and mass, the components were transferred into the fundamental block.

Decisions were made all throughout the design phase based on mathematical calculations. Both the strength of the Ecocube elements and the capacity of the slab to support them were calculated. The use of the finite element method decreased the risk level during the design and assembly phases of the prototype, which allowed the development team to spend its resources more effectively. 

Results and Benefits

The customer has received:

  • 3 models of the fundamental building component;
  • the findings of the strengths calculations;
  • a collection of technological and design documentation;
  • a working fundamental block prototype;
  • the developed automated manufacturing technology and a list of equipment with technological operations.
6 months

project duration

83 block

per hour (productive capacity)

30 days

to construct a house from scratch to the box

Have a project to do?

Fill out the form and a member from our sales team will get back to you

Thank you!
Your request has been submitted! We shall contact you shortly

Oops! Something went wrong... Try to reload this page and resubmit

FAQ

At EnCata, what kinds of contracts do you use? Is it a fixed-term or an agile contract?
Can you provide me with a certification of competence?
What level of training do your specialists have?
Is it possible for us to cooperate with EnCata’s team?
Is it possible to discuss the project with your technical team?
Can EnCata facilitate mass production?
Do you sign NDAs?
Patent or Develop first?
Does EnCata outsource electronics services?
Do you write program code, either software or firmware?
Are there hardware engineers in your team?
What should I do now that I've approached you with my project idea?
Can EnCata help me with fundraising?